• +968-77532775
  • info@alforsanprojects.com
  • Al Waheibi building Way No:5349 Al Khoudh-6, Muscat, Sultanate of Oman

Our premier projects

Over the past Four years in Oman, we have successfully installed numerous solar power systems in remote and inaccessible locations, delivering reliable energy to homes and businesses across the country. Our philosophy of simplifying technology for our customers has helped us become one of Oman’s largest independent technology providers and pioneers in the solar energy sector.

10 KWp Stand Alone PV System Project At Bahla

We, Al Forsan Al Asrah, completed our first project in Bahla on top of the mountains in 2021. This was a very challenging project due to its location at the mountain peak, and we successfully procured all the materials in a single attempt. The inverter used in this project was a 10 KW DEYE inverter, paired with Dyness Li-PO4 lithium-ion batteries. The inverter was three-phase, as per the client’s requirement for a three-phase connection. The system type was stand-alone. Despite the challenges, we completed the project within a duration of 7 days.

Client : Mr. Hamood

Main Contractor : M/s. Khimji Ramdas

Year of Execution : 2020-2021

Capacity : 10 KWp

10 KWp off-grid project in Yanqul, Ibri,

We, Al Forsan Al Asrah, completed another off-grid project in Yanqul, Ibri, on the mountain top in 2021. For this project, we used a 10 kW Growatt inverter along with Growatt LiFePO4 lithium-ion batteries. The inverter was a three-phase system, selected to match the client’s appliances, as they required a three-phase connection.

This project was part of a dam initiative, where the client’s requirement was to operate the dam gate, which is entirely powered by solar energy.

System Type: Stand-alone

Despite the challenging conditions, we successfully completed the project within 7 days.

Client : M/S Galfar Engineering SAOG

Main Contractor : M/s. Al Forsan Al Asrah

Year of Execution : 2021-2022

Capacity : 10 KWp

480 KWp Grid-Connected PV System Project At Sohar

One of the biggest projects AFAA Involved  in Oman is the rooftop project in the Sohar Industrial Area. This is a sheeted roof project. We adhered to all safety protocols and completed it within Short time. It was a highly challenging project, and we provided comprehensive training to all our workers to ensure adherence to Standard HSE procedures.

System Type:
(Grid-Connected PV System)

Client :  M/s. Bahwan Enterprises LLC

Year of Execution : 2022-2023

Capacity : 480 KWp

Total 25 KWp Grid-Connected PV System Projects At Sur

We completed five mosque projects in Sur. Each project was an RCC rooftop installation with a capacity of 5 kW. The inverters used were from Huawei, and the modules were provided by Longi Solar.

Each project was completed within 5 to 7 days.

System Type: (Grid-Connected PV System)
Client : Ministry of Auqaf

Main Contractor : M/s. continental shelf of solar tech

Year of Execution : 2022-2023

Capacity :Total 25 KWp (5 KWp Each)

Project Cost : 

10 KWp Grid-Connected PV System Project At Barka

We completed another 10 kWp project in Barka, near the Naseem Park area. This was also a rooftop project, but since the roof was made of RCC (Reinforced Cement Concrete), we had to prepare the foundations. These foundations were fabricated at our workshop and then transported to the site due to the lack of water sources at the location. We successfully completed the project in 15 days. The inverter used in this project was a 10 kW Huawei inverter, and the solar panels were from JA Solar.

System Type: Grid-Connected PV System
Client : Mr. mohammed ismaili

Main Contractor : M/s. Green Universe Enterprise

Year of Execution : 2023-2024

Capacity : 10 kW (550 Wp x 22 panels)

30 KWp Grid-Connected PV System Projects At Musannah

Another project we completed with a capacity of 30 kWp was in Musanah. This was also a rooftop project, but since the roof was made of RCC, we had to prepare the foundations. These foundations were prepared on-site for the client, then transported and installed. The foundation size was 350 x 350 x 350 mm.

We completed this project in 30 days, as the casting and curing of the foundations took around 17 days. During this time, we also procured the materials.

The inverter used in this project was a 50 kW Huawei inverter, as the client requested the capacity to accommodate future increases in the number of PV modules, and NAMA did not approve more than 30 kWp. The solar panels were from JA Solar.

System Type:
(Grid-Connected PV System)
Inverter: Huawei Sun 2000-50 KTL M1
PV Modules: JA Solar
Client : Mr Sayed

Main Contractor : M/s. Earc Sabla

Year of Execution : 2023-2024

Capacity: 30 kW (550 Wp x 56 panels)

We have worked on many solar PV projects of varying capacities across Oman.

⮚Installed Solar submersible Pump @ Rustaq

⮚Installed 25 KW On-Grid System @ Sur School

⮚Erection and Installation of Poles @ Muscat

⮚Installed BOSCH Solar water heater @ Madinat al Qaboos